1. The Operations tab will only populate if the Operations Section engaged is enabled within the Command And Safety area of the Operations section.
2. With no branches engaged you are able to document Staging Division and Special Resources from the Operations tab.
- Document the Date/Time, Unit, Personnel, and add any Notes.
3. When documenting any Date/Time fields select in the field or use the stopwatch icon to time stamp current date/time.
4. When selecting in the Date/Time field you are able to manually adjust any Date or Time fields.
5. To begin documenting Special Resources select in the field.
6. From the Special Resource modal begin documenting information.
- Select Close to save any Special Resource.
7. To add and additional Special Resources select the +Add button and repeat step 6.
8. To remove any Special Resources select the trash can icon.