Field Management - Risk Classification

Field Management - Risk Classification

Purpose

  1. The purpose of this Knowledge Base Article is to demonstrate how to modify the "Risk Classification" list for "Risk Assessment."


Related Article


Video



Instructions


1. Click on Admin.


Click on Admin.



2. Click on Field Management.


Click on Field Management.



3. Filter the Field Name list for "Risk Classification." and select apply.






4. Select Edit.


Select Edit.



5. Edit Field modal for Risk Classification.


Edit Field modal for Risk Classification.



6. Click on Add to add a new Risk Classification or Edit to edit a Risk Classification.


Click on Add to add a new Risk Classification or Edit to edit a Risk Classification.



7. Click on Icon to select the desire Icon.


Click on Icon to select the desire Icon.



8. Set the Value Range.
  1. Two numeric fields that are greater or equal to 0.
  2. The range can be empty if the Risk Classification is used manually only.
  3. If there is a value in To, there needs to be a value in From.
  4. If there is a value in From but To is empty, it means greater than the value in From.
  5. The ranges can’t overlap.

Set the Value Range.



9. Error message If a value is entered in the "To" field without a value in the "From" field.
The same value can be entered in both fields, if the values don't overlap.






10. Overlapping Values Error Message:






11. Manually setting the Risk Classification. Set the ranges From and To with the same values:
  1. Example: Low Risk





12. Default Values:






13. Enter Text or edit the Short Description.


Enter Text or edit the Short Description.



14. Enter Text or edit the Full Description.


Enter Text or edit the Full Description.



15. Click on Save when done.


Click on Save when done.


    • Related Articles

    • Risk Assessment - OVAP Scoring

      Purpose The purpose of this Knowledge Base Article is to demonstrate how to calculate the Risk Assessment Score for an Occupancy. Background OVAP Definition: Occupancy Vulnerability Assessment Profile Purpose: Risk assessment (AKA OVAP Scoring) is a ...
    • Risk Assessment - OVAP Scoring

      Purpose The purpose of this Knowledge Base Article is to demonstrate how to calculate the Risk Assessment Score for an Occupancy. Background OVAP Definition: Occupancy Vulnerability Assessment Profile Purpose: Risk assessment (AKA OVAP Scoring) is a ...
    • Field Management - Schedule To

      Heads Up! We are adding a new feature for Field Management! These changes will allow agencies to manage the Schedule To List for scheduling Inspections and reinspection's. Our new feature will be released on February 19, 2024. This article highlights ...
    • Field Management - Overview

      Purpose The purpose of this Knowledge Base Article is to provide an overview of Field Management including the basic management of fields within the First Due platform. Video Instructions 1. Click on Admin. 2. Click on Field Management. 3. Advanced ...
    • Field Management: Contact Types

      Purpose To demonstrate how to manage Preplan Contact Types. Note: This permission needs to be enabled for a user to manage preplan contact types: Pre-Planning - Manage Preplan Contacts Type. Video Instructions 1. Click on Admin. 2. Click on Field ...